VERIFICATION

We re-ran Cain's own savings studies through PULSE. The heat numbers hold; the money needs a stated convention.

Cain Industries publishes five savings analysis studies with the full input set — burner input, O₂ and excess air, flue temperatures, water flow and rise, fuel price, run hours — plus the BTU recovered and the payback they quote. That is enough to check a model against a third party on identical inputs, which is what this page does: their numbers on the left, PULSE on the right, no assumptions of ours inserted.

Inputs, exactly as Cain publishes them

StudyHeat sinkFlue gas Burner inputFuel · price · hours
RTR — 55,000 lb/h steam boilerBoiler feedwater · 118 GPM · 227 → 276.0 °F 509 → 343 °F70,000,000 BTU/h Kerosene · $0.70/therm · 4,000 h/yr
FCR — 500 HP steam boilerProcess water · 25 GPM · 120 → 168.6 °F 400 → 268 °F20,922,000 BTU/h Natural gas · $0.60/therm · 6,000 h/yr

Only the two boiler studies are used here. Cain's other three studies are engine and turbine exhaust, an application we do not sell.

Heat recovered: two independent balances

Two ways to reach the same BTU/h without trusting either party's answer: the water side (500 × GPM × ΔT) and the gas side (flue mass flow × cp × ΔT, with flue mass built from burner input, fuel heating value and the excess air Cain states).

StudyCain published Water sideGas side% of burner input
RTR 2,781,000 2,891,000 +4.0% 2,733,341 -1.7% 3.97 %
FCR 608,396 607,625 -0.1% 623,914 +2.6% 2.91 %

Water side lands within 4 % and the gas side within 3 % of Cain's published BTU/h on both studies. The heat recovery physics we use is Cain's own physics — that is the validation that matters before anyone lets a model size equipment.

Money: Cain's two studies use two different conventions

Recovered heat becomes a fuel saving in one of two ways. Heat credit treats every recovered BTU as a therm of fuel not bought. Fuel-side credit divides by boiler efficiency first, because a BTU recovered in the feedwater displaces 1/η BTU of fuel at the burner. The difference is 25 % at η = 0.80, so it has to be stated.

StudyCain quotedHeat credit ×hours Fuel-side credit ÷0.80Gap vs Cain (heat / fuel)
RTR $96,816 · 5.6 mo $77,868 · 6.9 mo $97,335 · 5.5 mo -19.6% / +0.5%
FCR $21,902 · 3.7 mo $21,902 · 3.7 mo $27,378 · 2.9 mo +0.0% / +25.0%

The FCR study matches the heat-credit method to the dollar; the RTR study only matches when the same recovered heat is divided by roughly 0.80. Same publisher, same page, two methods — which is exactly the ambiguity an audit has to remove. Our own pages always divide by the boiler efficiency and print η next to the number.

So can PULSE do a customer audit or a sizing study?

What this comparison proves is the arithmetic core: same inputs, same BTU/h, within a few percent, with the limiting side visible. What a paid audit still needs on top, and where we stand today:

Gas-side flue mass flow from burner input, O₂ and excess airProven above — implemented, ±3 %
Water-side limit (GPM × ΔT decides whether the sink can absorb the heat)Proven above — implemented
Dew-point check before any condensing claimImplemented; every case page carries the verdict
Fuel-side credit with η printedImplemented — this is where we are stricter than the source
Payback with real fuel price and run hoursImplemented
Measurement plan, baseline and uncertainty (M&V)Implemented as the VX-MV protocol
Equipment selection from a catalogue (C-WEP equivalent)Not built — sizing a model number is still a manufacturer task; we specify duty, temperatures and limits
Site survey inputs (fuel analysis, load profile, stack traverse)Manual — collected on site, typed in

Verdict: yes for measuring, re-modelling and auditing a savings claim; no for promising a model number off a catalogue. The honest boundary is the one we already publish: we are a systems integrator, not the manufacturer.

What the distributor adds to the picture

Clark WF sells Cain economizers alongside Hurst boilers, Oilon and Webster burners and Siemens controls, and their Cain page carries three details the manufacturer's own pages leave out:

The same page lists the sinks Cain engineers for — feedwater, cold make-up, process water, pool water, glycol and thermal fluids — and the fuels: natural gas, propane, digester gas, diesel and No. 2–6 oil. Those two lists are the practical checklist for the first five minutes of any site survey.

Sources

Method note: cp flue = 0.27 BTU/lb·°F; HHV 22,000 BTU/lb for natural gas and 19,800 BTU/lb for kerosene; stoichiometric air/fuel 15.6 and 15.0 lb/lb; flue mass = fuel mass × AFR × (1 + excess air) using Cain's stated excess air. Water side uses 500 × GPM × ΔT. Boiler efficiency for the fuel-side credit is 0.80, stated on every page that uses it.