IPMVP Option B for boiler heat recovery

Answer: Option B means every term in the saving equation is measured, not estimated: fuel flow, steam flow, feedwater flow and temperature, flue gas temperature in and out, oxygen. Savings = baseline adjusted to reporting conditions minus the measured reporting period, at 15-minute intervals, with a stated uncertainty of ±1.0%.

The four options, and why this one

IPMVP offers four approaches. Option A measures key parameters and estimates the rest; Option B measures all parameters of the savings; Option C measures the whole facility; Option D uses calibrated simulation. For a heat recovery retrofit the saving happens in one isolated stream — the flue — so Option B is the correct and cheapest defensible route: it isolates the measure and meters every term.

What the tag register contains

Fuel flow to the burner (mass flow for liquid fuel, volumetric plus composition for gas), steam flow and pressure, feedwater flow and temperature, make-up water flow, flue gas temperature at the exchanger inlet and outlet, flue gas oxygen, ambient temperature and barometric pressure. Each tag carries its range, calibration date and uncertainty; the register is annex A1 of the report.

How savings are computed

A baseline of twelve months is regressed against the drivers — steam output, ambient conditions, load pattern. In the reporting period the same drivers are measured, the baseline is adjusted to them, and the difference between adjusted baseline and measured fuel is the saving. Because the adjustment is by the drivers, a mild winter or a slower production week does not become a phantom saving.

What the ±1.0% means

It is the expanded uncertainty of the saving, propagated from the instrument uncertainties of the tags above, not a marketing tolerance. It is why a guaranteed saving is quoted below the central estimate — the guarantee sits at the lower confidence bound so that measurement noise never turns into a dispute.

Who sees the numbers

The same dataset feeds the live dashboard and the report, so the plant owner, the ESCO and the financing bank read one number. That is the point of Option B in an ESCO contract: the payment is computed from a measurement both sides can reproduce.